The frame construction prelims

OK, so the bungalow demolition, dig out, retaining walls, foundation pads etc. were also project stages to get this far, but they weren’t the start of a clear up, frame Glulam by Glulam check to see it’s all as it should be, so the frame can start going up this week. All being good (the rest of the week wind and rain forecast is lots of both, which isn’t ideal) the frame will start to go up on Wednesday.

Having 9 of the ecofab team on site certainly makes quick work of any site jobs.

2013-11-18 09.04.12 (2)


By the early afternoon the garage area was a tidy collection of most of the site material.

2013-11-18 15.38.29 (2)

and the last concrete slab steel work was ready for the pour (which should be tomorrow, Tuesday the 19th).

2013-11-18 15.39.47 (2)