Verticals for the top second floor going in. Also glulams across the ends and in other positions that are the top of the first floor and the bottom of the second floor.
2014-01-07 08.55.51 (2)

 

 

In the background the waves are enormous:

2014-01-07 09.03.27 (2)

 

The progress is towards putting in the next level of ceiling / floor panels:

2014-01-08 13.48.09 (2)

 

and from the front, you can see the first floor front steel has been put on:

2014-01-08 13.40.57-2

 

The groundwork’s are also progressing with the re-enforced concrete steps coming out of their shuttering:

2014-01-08 13.41.53 (2)