The last retaining walls are in

The SE corner (back left if you have your back to the sea) corner of the site has had the shuttering for the last section of retaining wall and the boundary wall finished this week:

2013-11-12 08.53.24 (2)

 

2013-11-13 08.39.49 (2)

The concrete has been poured into the shuttering.

2013-11-15 08.45.50 (2)

Shuttering has been taken down (and not yet tidied up, that was later).

2013-11-15 08.47.10 (2)

2013-11-16 10.28.16 (2)

Above the retaining walls the site is levelled out for the section of the first floor that extends here.

2013-11-13 08.35.55 (2)

More Glulam beams have been delivered.